Damaged overhead wires: Leiden-Duivendrecht-Lelystad (5 December 2023)
-
Disruption resolved Last update
Between Leiden Centraal and Lelystad Centrum the train traffic is fully resumed.
-
Delays decreasing
Between Leiden Centraal and Lelystad Centrum the restrictions are resolved.
Delays are decreasing.
Service is normal around 8:15 PM hours. -
Update
Between Leiden Centraal and Lelystad Centrum fewer intercities are running due to damaged overhead wires.
The extra travel time may be up to 30 minutes.
This will take until approximately 9:30 PM hours.Train measures
- Intercity 700 Groningen/Den Haag C. - Den Haag C./Groningen runs only once per hour between Lelystad Centrum and Den Haag Centraal
- Intercity 1800 Leeuwarden/Den Haag C. - Den Haag C./Leeuwarden runs only once per hour between Lelystad Centrum and Den Haag Centraal
-
Update
Between Leiden Centraal and Lelystad Centrum fewer intercities are running due to damaged overhead wires.
The extra travel time may be up to 30 minutes.
This will take until approximately 6:15 PM hours.Train measures
- Intercity 700 Groningen/Den Haag C. - Den Haag C./Groningen runs only once per hour between Lelystad Centrum and Den Haag Centraal
- Intercity 1800 Leeuwarden/Den Haag C. - Den Haag C./Leeuwarden runs only once per hour between Lelystad Centrum and Den Haag Centraal
-
Update
Between Leiden Centraal and Lelystad Centrum fewer intercities are running due to damaged overhead wires.
The extra travel time may be up to 30 minutes.
This will take until approximately 6:15 PM hours.Train measures
- Intercity 700 Den Haag C./Groningen - Groningen/Den Haag C. is cancelled between Lelystad Centrum and Den Haag Centraal
- Intercity 1800 Den Haag C./Leeuwarden - Leeuwarden/Den Haag C. is cancelled between Lelystad Centrum and Den Haag Centraal
-
Disruption
Between Leiden Centraal and Lelystad Centrum fewer intercities are running due to damaged overhead wires.
The extra travel time may be up to 30 minutes.
This will take until approximately 6:15 PM hours.
More about this disruption
Statistics
This disruption started at 2:05 PM on December 5, 2023 and took 6 hours, 15 minutes in total.
For statistics, this disruption is caused due to damaged overhead wires.
Affected lines
The following lines are affected by this disruption:
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.