Signal and level crossing failure: Utrecht-Hilversum (15 February)
-
Disruption resolved Last update
Between Utrecht Centraal and Hilversum the train traffic is fully resumed.
-
Delays decreasing
Between Utrecht Centraal and Hilversum the restrictions are resolved.
Delays are decreasing.
Service is normal around 6:00 PM hours. -
Update
Between Utrecht Centraal and Hilversum there are fewer trains running due to a signalling and level crossing failure.
This will take until approximately 6:00 PM hours.Train measures
- Sprinter 5700 Hoofddorp/Utrecht C. - Utrecht C./Hoofddorp is cancelled between Utrecht Centraal and Hilversum
-
Update
Between Utrecht Centraal and Hilversum there are fewer trains running due to a signalling and level crossing failure.
This will take at least until 6:00 PM hours.Train measures
- Sprinter 5700 Hoofddorp/Utrecht C. - Utrecht C./Hoofddorp is cancelled between Utrecht Centraal and Hilversum
-
Update
Between Utrecht Centraal and Hilversum there are fewer trains running due to a signalling and level crossing failure.
This will take until approximately 6:30 PM hours.Train measures
- Sprinter 5700 Hoofddorp/Utrecht C. - Utrecht C./Hoofddorp is cancelled between Utrecht Centraal and Hilversum
-
Update
Between Utrecht Centraal and Hilversum there are fewer trains running due to a signalling and level crossing failure.
This will take until approximately 7:30 PM hours.Train measures
- Sprinter 5700 Hoofddorp/Utrecht C. - Utrecht C./Hoofddorp is cancelled between Utrecht Centraal and Hilversum
-
Update
Between Utrecht Centraal and Hilversum there are fewer trains running due to a signalling and level crossing failure.
It is not known yet how long this will take.Train measures
- Sprinter 5700 Utrecht C./Hoofddorp - Hoofddorp/Utrecht C. is cancelled between Utrecht Centraal and Hilversum
-
Disruption
Between Utrecht Centraal and Hilversum there are delays and fewer trains are running due to a signalling and level crossing failure.
It is not known yet how long this will take.
More about this disruption
Statistics
This disruption started at 4:14 PM on February 15, 2024 and took 1 hour, 48 minutes in total.
For statistics, this disruption is caused due to a signal and level crossing failure.
Affected lines
The following lines are affected by this disruption:
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.