Signalling and points failure: Den Haag-Rotterdam; Schiphol-Rotterdam (HSL) (29 February)
-
Disruption resolved Last update
Between Schiphol Airport and Rotterdam Centraal the train traffic is fully resumed.
Between Delft and Rotterdam Centraal the train traffic is fully resumed. -
Delays decreasing
Between Schiphol Airport and Rotterdam Centraal the restrictions are resolved.
Between Delft and Rotterdam Centraal the restrictions are resolved.
Delays are decreasing.
Service is normal around 12:30 PM hours. -
Delays decreasing
Between Schiphol Airport and Rotterdam Centraal the restrictions are resolved.
Between Delft and Rotterdam Centraal the restrictions are resolved.
Delays are decreasing.
Service is normal around 12:15 PM hours. -
Update
Between Schiphol Airport and Rotterdam Centraal there are delays and fewer trains are running due to a signalling and points failure.
Between Delft and Rotterdam Centraal there are delays and fewer trains are running due to a signalling and points failure.
This will take until approximately 1:00 PM hours. -
Update
Between Schiphol Airport and Rotterdam Centraal there are delays and fewer trains are running due to a signalling and points failure.
Between Delft and Rotterdam Centraal there are delays and fewer trains are running due to a signalling and points failure.
This will take until approximately 3:15 PM hours. -
Update
Between Schiphol Airport and Rotterdam Centraal there is a service disruption due to a signalling and points failure.
Between Delft and Rotterdam Centraal there is a service disruption due to a signalling and points failure.
This will take until approximately 3:15 PM hours. -
Disruption
Between Schiphol Airport and Rotterdam Centraal there is a service disruption due to a signalling and points failure.
Between Rotterdam Centraal and Gouda there is a service disruption due to a signalling and points failure.
Between Delft and Rotterdam Centraal there is a service disruption due to a signalling and points failure.
This will take until approximately 3:15 PM hours.
More about this disruption
Statistics
This disruption started at 11:28 AM on February 29, 2024 and took 1 hour, 2 minutes in total.
For statistics, this disruption is caused due to a signalling and points failure.
Affected lines
The following lines are affected by this disruption:
Operators
This disruption affects trains operated by NS, NS International, Thalys and Eurostar.
Got delayed due to this disruption? You may be reimbursed.