Signal and level crossing failure: Arnhem-Zutphen (1 April)
-
Disruption resolved Last update
Between Arnhem Centraal and Dieren the train traffic is fully resumed.
-
Delays decreasing
Between Arnhem Centraal and Dieren the restrictions are resolved.
Delays are decreasing.
Service is normal around 5:45 PM hours. -
Update
Between Arnhem Centraal and Dieren no trains are running due to a signalling and level crossing failure.
This will take until approximately 6:00 PM hours.Train measures
- Intercity 3600 Zwolle/Roosendaal - Roosendaal/Zwolle is cancelled between Arnhem Centraal and Zutphen
- Sprinter 7600 Wijchen/Zutphen - Zutphen/Wijchen is cancelled between Arnhem Centraal and Dieren
-
Update
Between Arnhem Centraal and Dieren no trains are running due to a signalling and level crossing failure.
This will take until approximately 6:00 PM hours. -
Update
Between Arnhem Centraal and Dieren there are delays and fewer trains are running due to a signalling and level crossing failure.
This will take until approximately 6:00 PM hours. -
Disruption
Between Arnhem Centraal and Dieren there are delays and fewer trains are running due to a signalling and level crossing failure.
It is not known yet how long this will take.
More about this disruption
Statistics
This disruption started at 3:40 PM on April 1, 2024 and took 1 hour, 58 minutes in total.
For statistics, this disruption is caused due to a signal and level crossing failure.
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.