uitloop werkzaamheden

Over-running engineering works: Leiden-Den Haag HS; Den Haag-Rotterdam (17 April)

  1. Disruption resolved Last update

    Between Den Haag HS and Delft the train traffic is fully resumed.
    Between Den Haag Laan v NOI and Den Haag HS the train traffic is fully resumed.

  2. Delays decreasing

    Between Den Haag HS and Delft the restrictions are resolved.
    Between Den Haag Laan v NOI and Den Haag HS the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 6:00 AM hours.

  3. Delays decreasing

    Between Den Haag HS and Delft the restrictions are resolved.
    Between Den Haag Laan v NOI and Den Haag HS the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 6:30 AM hours.

  4. Update

    Between Den Haag HS and Delft there are fewer trains running due to over-running engineering works.
    Between Den Haag Laan v NOI and Den Haag HS there are fewer trains running due to over-running engineering works.
    This will take until approximately 6:30 AM hours.

  5. Update

    Between Den Haag HS and Delft there are fewer trains running due to over-running engineering works.
    Between Den Haag Laan v NOI and Den Haag HS there are fewer trains running due to over-running engineering works.
    This will take until approximately 6:00 AM hours.

  6. Update

    Between Den Haag HS and Delft there are fewer trains running due to over-running engineering works.
    Between Den Haag Laan v NOI and Den Haag HS there are fewer trains running due to over-running engineering works.
    This will take until approximately 6:15 AM hours.

  7. Disruption

    Between Den Haag Centraal and Den Haag HS there is a service disruption due to over-running engineering works.
    Between Den Haag HS and Delft there is a service disruption due to over-running engineering works.
    Between Den Haag Laan v NOI and Den Haag HS there is a service disruption due to over-running engineering works.
    This will take until approximately 6:15 AM hours.

More about this disruption

Statistics

This disruption started at 4:19 AM on April 17, 2024 and took 1 hour, 38 minutes in total.

For statistics, this disruption is caused due to over-running engineering works.

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights