Damaged railway bridge: Utrecht-Rotterdam; Utrecht-Den Haag (3 May)
-
Disruption resolved Last update
Between Utrecht Centraal and Rotterdam Centraal the train traffic is fully resumed.
Between Utrecht Centraal and Den Haag Centraal the train traffic is fully resumed. -
Delays decreasing
Between Utrecht Centraal and Rotterdam Centraal the restrictions are resolved.
Between Utrecht Centraal and Den Haag Centraal the restrictions are resolved.
Delays are decreasing.
Service is normal around 11:45 AM hours. -
Update
Between Utrecht Centraal and Rotterdam Centraal no intercities are running due to a damaged railway bridge.
Between Utrecht Centraal and Den Haag Centraal no intercities are running due to a damaged railway bridge.
This will take until approximately 12:30 PM hours.Train measures
- Intercity 500 Rotterdam C./Groningen - Groningen/Rotterdam C. is cancelled between Rotterdam Centraal and Utrecht Centraal
- Intercity 600 Rotterdam C./Leeuwarden - Leeuwarden/Rotterdam C. is cancelled between Rotterdam Centraal and Utrecht Centraal
- Intercity 1700 Den Haag C./Enschede - Enschede/Den Haag C. is cancelled between Den Haag Centraal and Utrecht Centraal
- Intercity 11700 Den Haag C./Schothorst - Schothorst/Den Haag C. is cancelled between Den Haag Centraal and Utrecht Centraal
-
Update
Between Utrecht Centraal and Rotterdam Centraal no intercities are running due to a damaged railway bridge.
Between Utrecht Centraal and Den Haag Centraal no intercities are running due to a damaged railway bridge.
This will take until approximately 12:30 PM hours. -
Update
Between Utrecht Centraal and Rotterdam Centraal no intercities are running due to a damaged railway bridge.
Between Utrecht Centraal and Den Haag Centraal far fewer trains are running due to a damaged railway bridge.
This will take until approximately 12:30 PM hours. -
Disruption
Between Gouda and Zoetermeer there is a service disruption due to a damaged railway bridge.
Between Rotterdam Centraal and Gouda there is a service disruption due to a damaged railway bridge.
This will take until approximately 12:30 PM hours.
More about this disruption
Statistics
This disruption started at 10:47 AM on May 3, 2024 and took 59 minutes in total.
For statistics, this disruption is caused due to a damaged railway bridge.
Affected lines
The following lines are affected by this disruption:
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.