wisselstoring

Points failure: Utrecht-Rhenen (10 May)

  1. Disruption resolved Last update

    Between Driebergen-Zeist and Veenendaal Centrum the train traffic is fully resumed.

  2. Delays decreasing

    Between Driebergen-Zeist and Veenendaal Centrum the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 8:45 AM hours.

  3. Delays decreasing

    Between Driebergen-Zeist and Veenendaal Centrum the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 8:45 AM hours.

    Advice

    Local buses are still running between Driebergen-Zeist, Maarn, Veenendaal West and Veenendaal Centrum.

  4. Update

    Between Driebergen-Zeist and Veenendaal Centrum no trains are running due to a points failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 8:45 AM hours.

    Advice

    Local buses are running between Driebergen-Zeist, Maarn, Veenendaal West and Veenendaal Centrum.

    Train measures

    • Sprinter 7300 Rhenen/Breukelen - Breukelen/Rhenen is cancelled between Driebergen-Zeist and Veenendaal Centrum
  5. Update

    Between Driebergen-Zeist and Veenendaal Centrum no trains are running due to a points failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 8:45 AM hours.

    Advice

    There is a very limited bus service between Driebergen-Zeist, Maarn, Veenendaal West and Veenendaal Centrum.

    Train measures

    • Sprinter 7300 Rhenen/Breukelen - Breukelen/Rhenen is cancelled between Driebergen-Zeist and Veenendaal Centrum
  6. Update

    Between Driebergen-Zeist and Veenendaal Centrum no trains are running due to a points failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 8:30 AM hours.

    Advice

    There is a very limited bus service between Driebergen-Zeist, Maarn, Veenendaal West and Veenendaal Centrum.

    Train measures

    • Sprinter 7300 Rhenen/Breukelen - Breukelen/Rhenen is cancelled between Driebergen-Zeist and Veenendaal Centrum
  7. Update

    Between Driebergen-Zeist and Veenendaal Centrum no trains are running due to a points failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 8:30 AM hours.

    Advice

    There is a very limited bus service between Driebergen-Zeist, Maarn, Veenendaal West, Veenendaal Centrum and Rhenen.

    Train measures

    • Sprinter 7300 Breukelen/Rhenen - Rhenen/Breukelen is cancelled between Driebergen-Zeist and Veenendaal Centrum
  8. Update

    Between Driebergen-Zeist and Veenendaal Centrum no trains are running due to a points failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 8:30 AM hours.

    Advice

    There is a very limited bus service between Driebergen-Zeist, Maarn, Veenendaal West, Veenendaal Centrum and Rhenen.

    Train measures

    • Sprinter 7300 Breukelen/Rhenen - Rhenen/Breukelen is cancelled between Driebergen-Zeist and Rhenen
  9. Update

    Between Driebergen-Zeist and Veenendaal Centrum no trains are running due to a points failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 8:30 AM hours.

    Train measures

    • Sprinter 7300 Rhenen/Breukelen - Breukelen/Rhenen is cancelled between Driebergen-Zeist and Rhenen
  10. Update

    Between Driebergen-Zeist and Veenendaal Centrum no trains are running due to a points failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 8:45 AM hours.

    Train measures

    • Sprinter 7300 Rhenen/Breukelen - Breukelen/Rhenen is cancelled between Driebergen-Zeist and Rhenen
  11. Update

    Between Driebergen-Zeist and Veenendaal Centrum no trains are running due to a points failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 8:45 AM hours.

  12. Update

    Between Maarn and Veenendaal Centrum no trains are running due to a points failure.
    This will take until approximately 9:15 AM hours.

  13. Disruption

    Between Maarn and Veenendaal Centrum there is a service disruption due to a points failure.
    This will take until approximately 9:15 AM hours.

More about this disruption

Statistics

This disruption started at 6:27 AM on May 10, 2024 and took 2 hours, 10 minutes in total.

For statistics, this disruption is caused due to a points failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights