sein- en wisselstoring

Signalling and points failure: Utrecht-Gouda (11 May)

  1. Disruption resolved Last update

    Between Utrecht Centraal and Gouda the train traffic is fully resumed.

  2. Delays decreasing

    Between Utrecht Centraal and Gouda the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 10:30 PM hours.

  3. Update

    Between Utrecht Centraal and Gouda far fewer trains are running due to a signalling and points failure.
    This will take until approximately 11:45 PM hours.

  4. Disruption

    Between Utrecht Centraal and Gouda far fewer trains are running due to a signalling and points failure.
    It is not known yet how long this will take.

More about this disruption

Statistics

This disruption started at 9:42 PM on May 11, 2024 and took 35 minutes in total.

For statistics, this disruption is caused due to a signalling and points failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights