seinstoring

Signal failure: Utrecht-Den Haag (20 June)

  1. Disruption resolved Last update

    Between Utrecht Centraal and Den Haag Centraal the train traffic is fully resumed.

  2. Delays decreasing

    Between Utrecht Centraal and Den Haag Centraal the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 5:00 PM hours.

  3. Update

    Between Utrecht Centraal and Den Haag Centraal no intercities are running due to a signal failure.
    This will take until approximately 5:30 PM hours.

    Train measures

    • Intercity 1700 Den Haag C./Enschede - Enschede/Den Haag C. is cancelled between Den Haag Centraal and Utrecht Centraal
    • Intercity 2000 Den Haag C./Utrecht C. - Utrecht C./Den Haag C. is cancelled between Den Haag Centraal and Utrecht Centraal
    • Intercity 11700 Den Haag C./Schothorst - Schothorst/Den Haag C. is cancelled between Den Haag Centraal and Utrecht Centraal
  4. Update

    Between Utrecht Centraal and Den Haag Centraal no intercities are running due to a signal failure.
    This will take until approximately 5:30 PM hours.

  5. Disruption

    Between Utrecht Centraal and Woerden there is a service disruption due to a signal failure.
    This will take until approximately 5:30 PM hours.

More about this disruption

Statistics

This disruption started at 2:34 PM on June 20, 2024 and took 2 hours, 19 minutes in total.

For statistics, this disruption is caused due to a signal failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights