Power failure: Zwolle-Groningen (29 July)
-
Disruption resolved Last update
Between Assen and Groningen Europapark the train traffic is fully resumed.
-
Delays decreasing
Between Assen and Groningen Europapark the restrictions are resolved.
Delays are decreasing.
Service is normal around 1:45 PM hours. -
Update
Between Assen and Groningen Europapark no trains are running due to a power failure.
This will take until approximately 2:00 PM hours.Train measures
- Intercity 500 Groningen/Rotterdam C. - Rotterdam C./Groningen is cancelled between Groningen and Assen
- Intercity 700 Groningen/Den Haag C. - Den Haag C./Groningen is cancelled between Groningen and Assen
- Sprinter 8100 Groningen/Zwolle - Zwolle/Groningen is cancelled between Groningen and Assen
-
Update
Between Assen and Groningen Europapark no trains are running due to a power failure.
This will take until approximately 2:00 PM hours.Train measures
- Intercity 500 Rotterdam C./Groningen - Groningen/Rotterdam C. is cancelled between Groningen and Assen
- Intercity 700 Den Haag C./Groningen - Groningen/Den Haag C. is cancelled between Groningen and Assen
- Sprinter 6200 Assen/Groningen - Groningen/Assen is cancelled between Groningen and Assen
- Sprinter 8100 Zwolle/Groningen - Groningen/Zwolle is cancelled between Groningen and Assen
-
Update
Between Assen and Groningen Europapark no trains are running due to a power failure.
This will take until approximately 2:00 PM hours.Train measures
- Intercity 500 Groningen/Rotterdam C. - Rotterdam C./Groningen is cancelled between Groningen and Assen
- Intercity 700 Groningen/Den Haag C. - Den Haag C./Groningen is cancelled between Groningen and Assen
- Sprinter 6200 Groningen/Assen - Assen/Groningen is cancelled between Groningen and Assen
- Sprinter 8100 Groningen/Zwolle - Zwolle/Groningen is cancelled between Groningen and Assen
-
Update
Between Assen and Groningen Europapark no trains are running due to a power failure.
This will take until approximately 3:00 PM hours.Train measures
- Intercity 500 Rotterdam C./Groningen - Groningen/Rotterdam C. is cancelled between Groningen and Assen
- Intercity 700 Den Haag C./Groningen - Groningen/Den Haag C. is cancelled between Groningen and Assen
- Sprinter 6200 Assen/Groningen - Groningen/Assen is cancelled between Groningen and Assen
- Sprinter 8100 Zwolle/Groningen - Groningen/Zwolle is cancelled between Groningen and Assen
-
Disruption resolved
Between Assen and Groningen Europapark the train traffic is fully resumed.
-
Delays decreasing
Between Assen and Groningen Europapark the restrictions are resolved.
Delays are decreasing.
Service is normal around 11:30 AM hours.Advice
Local buses are still running between Groningen, Haren and Assen.
-
Update
Between Assen and Groningen Europapark no trains are running due to a power failure.
This will take until approximately 12:00 PM hours.Advice
Local buses are running between Groningen, Haren and Assen.
Train measures
- Intercity 500 Groningen/Rotterdam C. - Rotterdam C./Groningen is cancelled between Groningen and Assen
- Intercity 700 Groningen/Den Haag C. - Den Haag C./Groningen is cancelled between Groningen and Assen
- Sprinter 6200 Groningen/Assen - Assen/Groningen is cancelled between Groningen and Assen
- Sprinter 8100 Groningen/Zwolle - Zwolle/Groningen is cancelled between Groningen and Assen
-
Update
Between Assen and Groningen Europapark no trains are running due to a power failure.
This will take until approximately 10:15 AM hours.Advice
Local buses are running between Groningen, Haren and Assen.
Train measures
- Intercity 500 Groningen/Rotterdam C. - Rotterdam C./Groningen is cancelled between Groningen and Assen
- Intercity 700 Groningen/Den Haag C. - Den Haag C./Groningen is cancelled between Groningen and Assen
- Sprinter 6200 Groningen/Assen - Assen/Groningen is cancelled between Groningen and Assen
- Sprinter 8100 Groningen/Zwolle - Zwolle/Groningen is cancelled between Groningen and Assen
-
Update
Between Assen and Groningen Europapark no trains are running due to a power failure.
This will take until approximately 10:15 AM hours.Train measures
- Intercity 500 Groningen/Rotterdam C. - Rotterdam C./Groningen is cancelled between Groningen and Assen
- Intercity 700 Groningen/Den Haag C. - Den Haag C./Groningen is cancelled between Groningen and Assen
- Sprinter 6200 Groningen/Assen - Assen/Groningen is cancelled between Groningen and Assen
- Sprinter 8100 Groningen/Zwolle - Zwolle/Groningen is cancelled between Groningen and Assen
-
Update
Between Assen and Groningen Europapark no trains are running due to a power failure.
This will take until approximately 10:15 AM hours.Train measures
- Intercity 500 Rotterdam C./Groningen - Groningen/Rotterdam C. is cancelled between Groningen and Assen
- Intercity 700 Den Haag C./Groningen - Groningen/Den Haag C. is cancelled between Groningen and Assen
- Sprinter 6200 Assen/Groningen - Groningen/Assen is cancelled between Groningen and Assen
- Sprinter 8100 Zwolle/Groningen - Groningen/Zwolle is cancelled between Groningen and Assen
-
Update
Between Assen and Groningen Europapark no trains are running due to a power failure.
This will take until approximately 10:15 AM hours. -
Update
Between Assen and Groningen Europapark no trains are running due to a power failure.
This will take until approximately 10:00 AM hours. -
Update
Between Assen and Groningen no trains are running due to a power failure.
This will take until approximately 10:00 AM hours. -
Disruption
Between Assen and Groningen there is a service disruption due to a power failure.
Updates will follow as more information becomes available.
More about this disruption
Statistics
This disruption started at 6:55 AM on July 29, 2024 and took 6 hours, 31 minutes in total.
For statistics, this disruption is caused due to a power failure.
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.