Signal failure: Maastricht-Liège / Luik (30 July)
-
Disruption resolved Last update
Between Maastricht and Visé the train traffic is fully resumed.
-
Delays decreasing
Between Maastricht and Visé the restrictions are resolved.
Delays are decreasing.
Service is normal around 8:30 PM hours.Advice
Local buses are still running between Maastricht Randwyck, Eijsden and Visé.
-
Update
Between Maastricht and Visé no trains are running due to a signal failure.
This will take until approximately 8:15 PM hours.Advice
Local buses are running between Maastricht Randwyck, Eijsden and Visé.
Train measures
- Sneltrein 18900 Maastricht/Aachen Hbf - Aachen Hbf/Maastricht is cancelled between Maastricht and Visé
- Stoptrein 32000 Kerkrade C./Randwyck - Randwyck/Kerkrade C. is cancelled between Maastricht and Maastricht Randwyck
-
Update
Between Maastricht and Visé no trains are running due to a signal failure.
This will take until approximately 8:15 PM hours.Train measures
- Sneltrein 18900 Maastricht/Aachen Hbf - Aachen Hbf/Maastricht is cancelled between Maastricht and Visé
- Stoptrein 32000 Kerkrade C./Randwyck - Randwyck/Kerkrade C. is cancelled between Maastricht and Maastricht Randwyck
-
Update
Between Maastricht and Visé no trains are running due to a signal failure.
This will take until approximately 8:45 PM hours.Train measures
- Sneltrein 18900 Aachen Hbf/Maastricht - Maastricht/Aachen Hbf is cancelled between Maastricht and Visé
- Stoptrein 32000 Randwyck/Kerkrade C. - Kerkrade C./Randwyck is cancelled between Maastricht and Maastricht Randwyck
-
Update
Between Maastricht and Visé no trains are running due to a signal failure.
This will take until approximately 8:45 PM hours.Train measures
- Sneltrein 18900 Maastricht/Aachen Hbf - Aachen Hbf/Maastricht is cancelled between Maastricht and Visé
- Stoptrein 32000 Kerkrade C./Randwyck - Randwyck/Kerkrade C. is cancelled between Maastricht and Maastricht Randwyck
-
Update
Between Maastricht and Visé no trains are running due to a signal failure.
This will take until approximately 8:45 PM hours. -
Disruption
Between Maastricht Randwyck and Visé there is a service disruption due to a signal failure.
This will take until approximately 8:45 PM hours.
More about this disruption
Statistics
This disruption started at 5:47 PM on July 30, 2024 and took 1 hour, 45 minutes in total.
For statistics, this disruption is caused due to a signal failure.
Affected lines
The following lines are affected by this disruption:
Operators
This disruption affects trains operated by Arriva and NMBS.
Got delayed due to this disruption? You may be reimbursed.