sein- en wisselstoring

Large signalling and points failure: Deventer - Enschede; Zwolle - Enschede. (3 September)

  1. Disruption resolved Last update

    Between Wierden and Almelo the train traffic is fully resumed.

  2. Delays decreasing

    Between Wierden and Almelo the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 12:15 PM hours.

  3. Update

    Between Wierden and Almelo no trains are running due to a large signalling and points failure.
    This will take until approximately 1:30 PM hours.

  4. Update

    Between Deventer and Wierden there are delays and fewer trains are running due to a large signalling and points failure.
    Between Wierden and Almelo there are delays and fewer trains are running due to a large signalling and points failure.
    This will take until approximately 1:30 PM hours.

  5. Update

    Between Deventer and Wierden there are delays and fewer trains are running due to a large signalling and points failure.
    Between Wierden and Almelo there are delays and fewer trains are running due to a large signalling and points failure.
    Between Zwolle and Wierden there are delays and fewer trains are running due to a large signalling and points failure.
    This will take until approximately 1:30 PM hours.

  6. Update

    Between Deventer and Wierden there is a service disruption due to a large signalling and points failure.
    Between Wierden and Almelo there is a service disruption due to a large signalling and points failure.
    Between Zwolle and Wierden there is a service disruption due to a large signalling and points failure.
    This will take until approximately 1:30 PM hours.

  7. Disruption

    Between Deventer and Wierden there is a service disruption due to a signal failure.
    Between Wierden and Almelo there is a service disruption due to a signal failure.
    Between Zwolle and Wierden there is a service disruption due to a signal failure.
    This will take until approximately 1:30 PM hours.

More about this disruption

Statistics

This disruption started at 11:18 AM on September 3, 2024 and took 37 minutes in total.

For statistics, this disruption is caused due to a large signalling and points failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS, NS International, Keolis and Blauwnet.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights