spoorproblemen buitenland

Railway problems abroad: Hengelo - Bielefeld (14 October)

  1. Disruption resolved Last update

    Between Hengelo and Oldenzaal the train traffic is fully resumed.

  2. Delays decreasing

    Between Hengelo and Oldenzaal the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 5:00 PM hours.

  3. Update

    Between Hengelo and Oldenzaal there are fewer local trains running due to railway problems abroad.
    The extra travel time is more than 60 minutes.
    This will take at least until 5:30 PM hours.

    Train measures

    • Stoptrein 20350-20397 Rheine - Hengelo is cancelled between Hengelo and Bielefeld Hbf
  4. Update

    Between Oldenzaal and Bad Bentheim no trains are running due to railway problems abroad.
    This will take at least until 5:30 PM hours.

    Train measures

    • Stoptrein 20350-20397 Hengelo - Bielefeld Hbf is cancelled between Hengelo and Bielefeld Hbf
  5. Delays decreasing

    Between Oldenzaal and Bad Bentheim the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 5:30 PM hours.

  6. Delays decreasing

    Between Oldenzaal and Bad Bentheim the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 3:30 PM hours.

  7. Update

    Between Oldenzaal and Bad Bentheim no trains are running due to railway problems abroad.
    This will take at least until 3:30 PM hours.

    Train measures

    • Stoptrein 20350-20397 Rheine - Hengelo is cancelled between Hengelo and Bielefeld Hbf
  8. Update

    Between Oldenzaal and Bielefeld Hbf no trains are running due to railway problems abroad.
    This will take at least until 3:30 PM hours.

    Train measures

    • Stoptrein 20350-20397 Rheine - Hengelo is cancelled between Hengelo and Bielefeld Hbf
  9. Update

    Between Oldenzaal and Bielefeld Hbf no trains are running due to railway problems abroad.
    This will take at least until 3:30 PM hours.

  10. Disruption

    Between Hengelo and Bad Bentheim no trains are running due to railway problems abroad.
    This will take at least until 3:30 PM hours.

More about this disruption

Statistics

This disruption started at 1:54 PM on October 14, 2024 and took 3 hours, 3 minutes in total.

For statistics, this disruption is caused due to railway problems abroad.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS International, Deutsche Bahn, eurobahn, Keolis and Blauwnet.

Got delayed due to this disruption? You may be reimbursed.