signalling and points failure

Signalling and points failure: Zwolle-Almelo (28 May 2013)

  1. Update Last update

    Door een sein- en wisselstoring rijden er geen treinen tussen Raalte en Nijverdal. Deze situatie duurt naar verwachting tot 18:00 uur.Doorgaande reizigers tussen Zwolle en Almelo kunnen omreizen via Deventer.

More about this disruption

Statistics

This disruption started at 3:46 PM on May 28, 2013 and took 21 minutes in total.

For statistics, this disruption is caused due to a signalling and points failure.