Engineering works: Arnhem - Duisburg - Düsseldorf
Situation
Between Emmerich and Wesel buses are running due to engineering works.
The extra travel time is about 60 minutes.
Period
Between Thursday, August 15, 2024 7:30 PM hours and Saturday, August 17, 2024 11:10 PM hours.
Advice
Between Emmerich and Wesel, VIAS is operating replacement buses. At 22:45, a VIAS stop bus will run from Arnhem C via Zevenaar to Duisburg Hbf.
Modified timetable
The timetable has not been modified for these engineering works.
More about these engineering works
Plan your trip
Plan your trip in advance and use the journey planner.
During your trip, you can stay up-to-date by checking live departures or by using the Rijden de Treinen mobile app for iOS and Android.
Affected lines
The following lines are affected by these engineering works:
Time periods
These engineering works are in effect between:
- Thursday, August 15, 2024 7:30 PM to Thursday, August 15, 2024 11:00 PM
- Friday, August 16, 2024 8:30 PM to Friday, August 16, 2024 11:10 PM
- Saturday, August 17, 2024 8:30 PM to Saturday, August 17, 2024 11:10 PM