seinstoring

Signal failure: Venlo-Mönchengladbach-Düsseldorf (24 January 2019)

  1. Disruption resolved Last update

    Between Venlo and Kaldenkirchen the restrictions are resolved.

  2. Delays decreasing

    Between Venlo and Kaldenkirchen the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 12:45 PM hours.

  3. Update

    Between Venlo and Kaldenkirchen no trains are running due to a signal failure.
    The extra travel time is more than 60 minutes.
    Updates will follow as more information becomes available.

    Train measures

    • Stoptrein 20060-20099 Venlo - Hamm (Westf.) is cancelled between Venlo and Kaldenkirchen
  4. Disruption

    Between Venlo and Kaldenkirchen no trains are running due to a signal failure.
    The extra travel time is more than 60 minutes.
    Updates will follow as more information becomes available.

More about this disruption

Statistics

This disruption started at 12:28 PM on January 24, 2019 and took 17 minutes in total.

For statistics, this disruption is caused due to a signal failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by eurobahn.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights