boom op het spoor

Tree on the track: Venlo-Mönchengladbach-Düsseldorf (21 October 2021)

  1. Disruption resolved Last update

    Between Venlo and Mönchengladbach Hbf the train traffic is fully resumed.

  2. Delays decreasing

    Between Venlo and Mönchengladbach Hbf the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 9:15 AM hours.

  3. Update

    Between Venlo and Mönchengladbach Hbf no trains are running due to a tree on the track.
    This will take until approximately 10:00 AM hours.

  4. Update

    Between Venlo and Mönchengladbach Hbf no trains are running due to a tree on the track.
    This will take until approximately 10:00 AM hours.

    Train measures

    • Stoptrein 450-499 Roosendaal - Antwerpen-C./Puurs is cancelled between Roosendaal and Essen (B)
  5. Disruption

    Between Venlo and Mönchengladbach Hbf no trains are running due to a tree on the track.
    This will take until approximately 10:00 AM hours.

More about this disruption

Statistics

This disruption started at 8:43 AM on October 21, 2021 and took 30 minutes in total.

For statistics, this disruption is caused due to a tree on the track.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by eurobahn.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights