stroomstoring

Power failure: Venlo-Roermond; Amsterdam-Venlo-Mönchengladbach-Köln (10 July 2023)

  1. Disruption resolved Last update

    Between Venlo and Tegelen the train traffic is fully resumed.
    Between Venlo and Kaldenkirchen the train traffic is fully resumed.

  2. Delays decreasing

    Between Venlo and Tegelen the restrictions are resolved.
    Between Venlo and Kaldenkirchen the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 10:00 PM hours.

  3. Update

    Between Venlo and Tegelen no trains are running due to a power failure.
    Between Venlo and Kaldenkirchen no trains are running due to a power failure.
    This will take until approximately 10:00 PM hours.

  4. Update

    Between Venlo and Tegelen there are fewer trains running due to a power failure.
    Between Venlo and Kaldenkirchen no trains are running due to a power failure.
    This will take until approximately 10:00 PM hours.

  5. Update

    Between Venlo and Tegelen no trains are running due to a power failure.
    Between Venlo and Kaldenkirchen no trains are running due to a power failure.
    This will take until approximately 10:00 PM hours.

  6. Update

    Between Venlo and Tegelen no trains are running due to a power failure.
    Between Blerick and Venlo no trains are running due to a power failure.
    Between Venlo and Kaldenkirchen no trains are running due to a power failure.
    This will take until approximately 10:30 PM hours.

  7. Update

    From and to Venlo far fewer trains are running due to a power failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 10:30 PM hours.

  8. Update

    Between Venlo and Tegelen no trains are running due to a power failure.
    This will take until approximately 10:30 PM hours.

  9. Disruption

    From and to Venlo no trains are running due to a power failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 10:30 PM hours.

More about this disruption

Statistics

This disruption started at 8:20 PM on July 10, 2023 and took 2 hours, 10 minutes in total.

For statistics, this disruption is caused due to a power failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by Arriva and eurobahn.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights