tekort personeel

Staffing problems: Venlo-Mönchengladbach-Düsseldorf (10 July)

  1. Disruption resolved Last update

    Between Venlo and Mönchengladbach Hbf the train traffic is fully resumed.

  2. Delays decreasing

    Between Venlo and Mönchengladbach Hbf the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 2:30 PM hours.

  3. Update

    Between Venlo and Mönchengladbach Hbf there are fewer trains running due to a staff shortage.
    The extra travel time may be up to 60 minutes.
    Service is normal around 2:30 PM hours.

  4. Update

    Between Venlo and Mönchengladbach Hbf there are fewer trains running due to a staff shortage.
    The extra travel time may be up to 60 minutes.
    This will take until approximately 2:30 PM hours.

  5. Update

    Between Venlo and Mönchengladbach Hbf there are fewer trains running due to a staff shortage.
    The extra travel time may be up to 60 minutes.
    This will take until approximately 5:00 PM hours.

  6. Disruption

    From and to Venlo there are fewer trains running due to a staff shortage.
    The extra travel time may be up to 60 minutes.
    This will take until approximately 5:00 PM hours.

More about this disruption

Statistics

This disruption started at 5:27 AM on July 10, 2024 and took 8 hours, 58 minutes in total.

For statistics, this disruption is caused due to staffing problems.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by eurobahn.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights