Staffing problems: Venlo-Mönchengladbach-Düsseldorf (25 August)
-
Disruption resolved Last update
Between Venlo and Mönchengladbach Hbf the train traffic is fully resumed.
-
Update
Between Venlo and Mönchengladbach Hbf there are fewer trains running due to a staff shortage.
This will take the rest of the day.Advice
Buses are running between Venlo, Kaldenkirchen, Breyell, Boisheim, Dülken, Viersen and Mönchengladbach Hbf.
Train measures
- Sneltrein 20060-20099 Hamm (Westf.)/Venlo - Venlo/Hamm (Westf.) is cancelled between Venlo and Mönchengladbach Hbf
-
Update
Between Venlo and Mönchengladbach Hbf there are fewer trains running due to a staff shortage.
This will take at least until 10:30 PM hours.Advice
Buses are running between Venlo, Kaldenkirchen, Breyell, Boisheim, Dülken, Viersen and Mönchengladbach Hbf.
Train measures
- Sneltrein 20060-20099 Hamm (Westf.)/Venlo - Venlo/Hamm (Westf.) is cancelled between Venlo and Mönchengladbach Hbf
-
Disruption
Between Venlo and Mönchengladbach Hbf there are fewer trains running due to a staff shortage.
This will take at least until 10:00 PM hours.Advice
Buses are running between Venlo, Kaldenkirchen, Breyell, Boisheim, Dülken, Viersen and Mönchengladbach Hbf.
More about this disruption
Statistics
This disruption started at 2:03 PM on August 25, 2024 and took 8 hours, 59 minutes in total.
For statistics, this disruption is caused due to staffing problems.
Operators
This disruption affects trains operated by eurobahn.
Got delayed due to this disruption? You may be reimbursed.