Staffing problems: Venlo - Mönchengladbach - Düsseldorf (17 December)
-
Disruption resolved Last update
Between Venlo and Kaldenkirchen the train traffic is fully resumed.
-
Delays decreasing
Between Venlo and Kaldenkirchen the restrictions are resolved.
Delays are decreasing.
Service is normal around 2:15 PM hours.Advice
Buses are still running between Venlo and Kaldenkirchen.
-
Update
Between Venlo and Kaldenkirchen there are fewer trains running due to a staff shortage.
The extra travel time is about 60 minutes.
This will take until approximately 2:15 PM hours.Advice
Buses are running between Venlo and Kaldenkirchen.
Train measures
- Sneltrein 20060-20099 Hamm (Westf.) - Venlo runs less often between Venlo and Kaldenkirchen
-
Update
Between Venlo and Kaldenkirchen there are fewer trains running due to a staff shortage.
The extra travel time is about 60 minutes.
This will take until approximately 2:15 PM hours.Train measures
- Sneltrein 20060-20099 Hamm (Westf.) - Venlo runs less often between Venlo and Kaldenkirchen
-
Disruption
Between Venlo and Kaldenkirchen there are fewer trains running due to a staff shortage.
The extra travel time is about 60 minutes.
This will take until approximately 2:15 PM hours.Train measures
- Stoptrein 20000-20049 Düsseldorf Hbf - Arnhem C. runs less often between Venlo and Kaldenkirchen
More about this disruption
Statistics
This disruption started at 7:25 AM on December 17, 2024 and took 7 hours, 24 minutes in total.
For statistics, this disruption is caused due to staffing problems.
Operators
This disruption affects trains operated by eurobahn.
Got delayed due to this disruption? You may be reimbursed.